Construction Control Guidelines For Environmental Logistics





Trash / Recycling For Environmental Logistics

The Plot Developer shall be responsible for complying with the Master Owner's Environmental Impact Study, all local environmental standards, and Environmental Management Plan and be approved by Local Govt. Agency. A copy of the study is available for review at the Master Developer's Project Managers office.

Construction Control Guidelines For Environmental Logistics

The Plot Developer shall provide trash receptacles on each floor of the building at sufficient frequency to discourage any stockpiling of waste. Stockpiling of waste where it creates a risk to health and / or safety will not be tolerated, and works on the offending site may be suspended.

  • The Plot Developer shall be responsible for removal of all debris from the site.
  • Trash and debris must not be allowed to accumulate.

Master Developer strongly advocate that, within their trash plans, Plot Developers incorporate the provision of separate receptacles for:

  1. Wood
  2. Cardboard
  3. Metal
  4. Drywall
  5. Other Materials

Ready-mix concrete trucks shall not be allowed to discharge any left over concrete at the Site. Any discharge from the concrete pump should be disposed of in a manner acceptable to the Master Developer's Project Manager.

The Plot Developer shall be responsible for all cleaning and garbage removal.

Each Plot Developer is required to clean his work area and remove accumulated debris on a daily basis.

Each Plot Developer is responsible to ensure that areas designated for tea breaks, lunch etc. for his workers are kept clean and hygienic at all times.

Those items considered to be too heavy or big for the trash bins shall be removed from the Site directly by each Plot Developer. The Plot Developer shall perform cleaning of areas around each site office.

The Plot Developer shall place skips around the construction areas and near the site offices with sufficient frequency. The Plot Developer shall, at the end of each day's work, empty the skips and haul the garbage and debris off-site.

The Plot Developer shall store construction waste and debris in a workman like manner, so as not to cause any fire hazard or any other encumbrances. Disposal of waste and debris should be done in a timely manner as permissible by the Site logistics and schedule.

The Plot Developer shall provide mini-dumpster on a daily basis for use (on each floor) and ensure disposal of debris on a daily basis or as directed by the Master Developer's Project Manager.

Housekeeping and cleanliness are of critical importance; the Plot Developer shall be responsible for maintaining the entire plot site and adjacent work areas in a clean and safe condition.

The Plot Developer is entirely responsible for the pest control of his Site.

Every effort shall be made by each Plot Developer to prevent the presence of vermin, rodents, mosquitoes and other pests on his Site.

The Plot Developer must ensure to install shoots to be used for construction debris collection from higher floors. No free fall of debris shall be permitted.

The Plot Developer shall take all reasonable steps to protect the environment on and off the site and to avoid damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes arising as a sequence of his method of operation.

Pollution Control For Environmental Logistics

The Plot Developers and their Contractors to comply with all local Pollution Control Laws and regulations.

Spillage For Environmental Logistics

The Plot Developer shall ensure at all times that spillage of concrete, oils or other deleterious material does not occur into any new or existing drainage, duct system or water course. Nevertheless, should any drainage, duct system or water course be contaminated by such materials, the Plot Developer shall take all necessary action to clean the drainage, duct system or water course at his own expense.

The Plot Developer shall ensure that there is no spillage of oil or any other contaminant onto any roadway.

Dust For Environmental Logistics

The Plot Developer shall employ the best practical means to minimize dust pollution due to his operations.

The Plot Developer shall keep clean all access roads and ways to his construction area. Preventative measures such as spraying by water truck will be required.

While working on building exteriors, dust screens shall be installed by the Plot Developer.

Noise For Environmental Logistics

The Plot Developer shall employ the best practical means to minimize noise and vibration produced by his operations. All plant and equipment supplied by the Plot Developer for use on the Works shall be effectively "sound reduced" by means of silencers, mufflers, acoustic linings or shields, acoustic sheds or screens, etc. The Plot Developer will comply with all current and relevant requirements and regulations applicable to noise control on construction sites.
 